Review of River Surface Cleaning works at Haridwar & Rishikesh & its approval

  • Contract awarded to M/s Ashwath Infratech on 13.12.16 by NMCG for three years.
  • Cleaning to be done by mechanized trash skimmers and trash booms.
  • Manual cleaning at one site in Rishikesh was started on 01.1.17 and at one site in Haridwar on 27.1.17.
  • Trash booms one each at Lalta Rao bridge, Haridwar and Triveni Ghat, Rishikesh installed on 29.03.2017.
  • One Trash Skimmer each installed at Haridwar & Rishikesh on 01.05.2017.
  • Later on Skimmer from Rishikesh has been shifted to Delhi.
  • Bipartite agreement between NMCG and M/s Ashwath Infratech has been entered in April 2017
  • Execution of Tripartite agreement between SPMG, ULBs and the firm M/s Infratech is under process. 

Publish Date: 15-02-2018